the May 13th Delaware County
Delaware County (OH) Board of Commissioners · 2026-05-13
Transcript
Delaware County TID Meeting- May 13, 2026
Transportation Improvement District
meeting. If we could all please rise if
you're able for the Pledge of
Allegiance.
>> I pledge allegiance to the flag of the
United States of America,
and to the republic for which it stands,
one nation under God, indivisible, with
liberty and justice for all.
>> Well, good morning, everybody. I'm Tracy
Davies, the vice chair. Next to me I
have Saki who's the secretary and
treasurer, and then we have the public
members of our board, Pat Blaney and Tom
Price.
Uh our chairperson, Chris Bowser man, is
unable to be here today. And also for
our board members, just uh staffing
change, Brandy Wilson with the
commissioner's office, she left to move
to Florida, and so you all remember Ali
Glusich, she's back in helping us out
with the TID.
All right, first on the agenda we have
the election of officers for the term of
May 13th to
2026 to May 12th, 2027.
Um
I'll leave it up to the group if we want
to do a slate of nominations or we
>> make a motion to appoint the current
officers to another term
on this board.
>> Okay, we have a motion.
Is there a second?
>> Second.
>> Any discussion? That would be continuing
to have Chris Bowser man as chairperson,
myself, Tracy Davies, as vice
chairperson, and uh Saki as the
secretary treasurer.
Any further discussion?
All in favor?
>> I.
>> I.
>> Motion carries. Great.
Do we have anyone from the public who
would like to comment today.
No?
Okay.
Next, we have approval of minutes from
the March 11th, 2026 meeting. I don't
know if you've had an opportunity to
review those minutes, but uh
if there aren't any changes or
corrections, I'll take a motion to
approve the minutes.
>> Move to accept the minutes.
>> Second.
>> We have a motion and a second. Any
further discussion?
All in favor?
>> Aye.
>> Aye.
>> Any opposed? Okay, motion carries.
Do we have any reports from our board
members
today?
No?
Nothing at this time? Okay.
Secretary-Treasurer's report.
>> The current cash balance is
$5,833,834.44.
And we're
our auditors are currently auditing us
and wrapping up. So, hopefully at the
next board meeting, I'll be able to
report on that.
>> Any questions?
>> Move to accept the Secretary-Treasurer's
report.
>> Second.
>> Any discussion?
All in favor?
>> Aye.
>> Aye.
>> Motion carries. Thank you.
Moving on to staff report and maybe some
introductions, Rob Riley.
>> All right. Well, uh good morning. Thank
you, Madam Chair. Uh the uh it is my
pleasure to recognize some of our
uh summer interns. Uh I'll ask them to
stand up and uh I'm going to pick on
them a little bit and
ask them to uh
tell us their name and uh where they're
from, where they're going to school, and
anything else uh you want to share with
us. So, start with the guy on the end.
He's one of our
>> If you could come to the podium so cuz
we are
we
>> for our massive viewing audience, we
want to make sure that they can hear
you.
>> I'll face this way.
>> Yes.
>> Okay.
Uh my name is Will Music.
Um I live in Ostrander, so just west of
Delaware.
Um
This is my second summer with the
county. It's been a great experience and
I am studying civil engineering at Ohio
University. I'll be a junior next year.
>> Well, welcome. Good to see you. Thank
you.
>> Good morning. Uh my name is Nate
Hickman. I'm from Cardington, Ohio, so
just north of Delaware.
Um this is my second summer interning
here and uh
I go to Ohio University where I'm
studying environmental science and I'm
heading into my senior year.
>> Great.
>> Thank you.
>> Well, welcome back. Thank you.
>> Hello. Hi, I'm Cadence Ford. I live in
Delaware City. I This is also my second
year interning with the county and I go
to the University of Pittsburgh for
chemical engineering and I will be a
junior next year.
>> Great. Well, welcome back.
>> Thank you.
>> It's nice to see three people back. We
must not have scared them away, so good
job, engineer's office.
>> Yeah, we're very glad to have uh our our
young folks back and
it's uh
Chris and I remark from time to time
it's kind of nice to get some young
blood in the office and
uh
feel the energy, I guess, of youthful
exuberance, I guess, so
but uh it's been fun. We have a lot of
uh projects lined up for our interns
this summer and uh it'll be fun, so
um
So, I will take uh
a few moments just to run through the
staff report uh
since the last meeting.
Um
So, uh as you know, we have a number of
active projects.
Just run through these quickly. I know
you're all aware of these current
projects. Silken Heartland regional
projects. These are the two roundabouts
on County Line Road, Delaware Licking.
Those are currently under construction.
We are working
currently at Center Village Road.
That should be
hopefully done and wrapped up by
July of this year. The crews will then
move on to the Fantazier Road
intersection and have that done
hopefully in September.
I-71 36-37 interchange. If you've driven
past, you know there's a lot of
activity, a lot of progress has been
made especially in the last month or so.
All of the new bridge beams were set
over about the last month for the new
overpass.
And so that's moving along very well.
Still on schedule for completion third
quarter of 2027.
Phase B and C.
Phase B is the next segment to the west
that will run west to 3B and K.
ODOT is currently working on
right-of-way acquisition for that phase.
And we do expect that will be ready to
go to construction in 2027. So more to
come on that. Currently working through
the the property purchase
and some utility relocation later this
year.
And then last but not least phase C,
which is the final segment to the west.
Plans are currently in design.
We will be
probably moving into right-of-way
acquisition about a year from now, a
year and a half from now on that phase
and tentatively starting construction in
2029.
So
if there's any questions on that, that's
kind of a snapshot of where we're at.
>> Rob, any updates on funding for phase B?
>> Not yet. You'll note note in the report
that ODOT did apply for
what the Federal Highway Administration
calls their build program. These are
grants that are
allocated directly by the USDOT to
states and local agencies. ODOT
submitted for that program, have not yet
heard back on on the success of that
application, but we'll keep our fingers
crossed on that.
>> Any questions?
Continue on, please.
>> Moving on, Orange Road Railroad grade
separation. We continue to make progress
on that project, no significant updates.
We are
will be going into
acquisition of right-of-way for the
remaining properties that are needed
probably later this year
with construction starting 2028.
And then finally, Stockwell Road
improvements. We do have resolution for
your consideration today, which would
authorize the county engineer to go out
to bid,
but the plans been completed, the
right-of-way has been acquired, and we
are
at this time really just awaiting the
OPWC
grant agreement award, which typically
comes out around the 1st of July. That
would go to Trenton Township. Trenton
was the applicant for that
in cooperation with the other three
townships, but pending
we would like to go to bid on that, get
the bids advertised and opened prior to
that time, so
at our July meeting, we would hope to
have a contract ready to award at that
time.
Moving on to potential future projects,
and I say potential because these are
not yet
not yet solidified, but
I've spoken to you about two of these
three. Bunny Station Road again.
This is involving the
uh, fifth Olentangy Local School
District High School.
Uh,
the work would involve widening Buddy
Station Road for
turn lanes in into the school.
Uh, because of where their entrances
sit, uh, we've had some discussions with
the school district. We've had
discussion with Liberty Township and um,
City of Delaware
about
uh, trying to make that section of road
a three-lane section with a continuous
center turn lane.
Uh, basically starting at the Seldom
Seen Parkway roundabout going west, uh,
not quite a half a mile, roughly half a
mile.
Um, which would uh, address what we know
is the case is high schools generally a
lot of traffic. There's a lot of cars
coming in and out throughout the day.
And so having that uh, turn lane would
make that really a better uh, situation
for really everyone.
So,
uh, I
believe we talked uh, in brief at the
last meeting about the idea of the TID
uh, assisting uh, Olentangy schools and
the townships with acquisition of
right-of-way.
And um,
I had a recent meeting with uh,
Olentangy Local Schools as well as
Liberty Township. I think there's
uh,
concurrence and and I think the time uh,
is quickly approaching where we will as
board need to make a decision on whether
we want to do that. And I would
uh, say this, you know, uh,
we we make every effort uh, when we
uh, try to purchase right-of-way to make
a fair offer, uh, negotiate a fair
settlement. Uh, sometimes that happens.
I would say the majority majority of
time that does happen. We're able to
reach agreement.
Uh, sometimes it does not. Sometimes the
the offer and
the owner's expectation of compensation
are two different, and so that um
sometimes results in us having to move
forward with the project,
um filing what uh you you may know is
called appropriation,
and then moving ahead with the project
while we continue to try to negotiate a
settlement. So,
um I bring that up because that would be
if if the board does wish to proceed uh
in this manner, that would be something
this board would need to consider
um if there is uh any appropriation
action, I believe
uh we will work with prosecutor's office
to either
uh
get representation directly uh from the
prosecutor's office or potentially hire
independent counsel if if needed. Uh I
have not gotten that far yet, but I did
want to make you aware of that
possibility. So,
uh really this is still in the
discussion phase. Um not recommending
any action today, but I have outlined in
the report
sort of the framework of a potential
agreement, uh and I'm I'm interested in
hearing your your feedback on that.
>> Question. In the report, it says
Olentangy would acquire the necessary
right-of-way. So, that's not the case?
>> If it does say that, I that is an error.
Uh
>> to obtain
and pay for plans, surveys, legal
descriptions, etc. to acquire necessary
right-of-way.
>> They would yes, they would uh Olentangy
Local Schools is is paying for the
design and the actual
plans and right-of-way plans and as well
as the legal descriptions, all the
paperwork that would be needed to
acquire the right-of-way. They would not
actually be doing the right-of-way
acquisition per se. That that would be
something that
we would be doing under this proposal.
I'm I'm sorry for that for the confusion
there.
But the uh school district would be
reimbursing the TID. I want to make sure
that's clear. Uh the arrangement we've
discussed to date has been that
Olentangy would reimburse uh the TID.
Olentangy uh they
Obviously they're in the business of
educating kids. They're not necessarily
in the business of following all the
statutory procedures that go with
acquiring purchasing road right-of-way
and so that's really the the source of
this discussion.
>> If the TID were were not to do it, who
would be the entity that would do it?
The Township?
>> I think that would be the next option
would be for the two Townships because
there's two Townships involved Delaware
Township and Liberty.
That would be sort of the next option.
>> In that case they're still relying on
the County Engineers offices
as
your their engineering.
>> Correct.
>> Chairman.
>> Yes.
>> The other
what five
schools that we built for
it was built for Olentangy there was no
need for us to be step in on those was
there?
>> There was not.
I would call this somewhat of a unique
circumstance because it's on a Township
line road partially within the city.
More jurisdictions on this than is
typical. You'll recall all of the
project we did on Bean Oller a couple of
years ago.
That was a case where there was really
only believe there were two two parcels
involved. The county did at that time
step in the Engineers office handled the
acquisition of right-of-way
on that and then you recall the TID
we handled the construction contract
were reimbursed by the
by the school district as well as
Townships and the OPWC grant. So,
um you're you're right, Tom. This is
This is something different, for sure.
>> Does the property just in front of the
school in the picture here then doesn't
extend
onto Sawmill where the three-lane
or the third lane will be
planned for?
>> So, if you look at the graphic,
uh
where it says entrance two, uh from that
portion going east towards the
roundabout, that's currently two lanes.
Uh it starts to widen out once you get
to
you can kind of see where it hits the
the field uh just to the north and west
of the roundabout. Uh that's where it
goes to what what I what I call a full
two-lane section.
The plan would be to kind of blend into
that.
Uh
you know, stop the three-lane section
where it it starts you hit the the
median or the splitter island. It would
go back to two-lane section.
Uh but there would be under the proposed
uh improvement a continuous three-lane
section essentially from that the west
end of that splitter island all the way
west across the school frontage.
>> So, there'd be right-of-way acquisition
there, too?
>> Yes.
>> I understand the need for someone to
step up to the plate.
Not that I couldn't get there. I'm a
little hesitant for the TID board to be
taking property if it gets to that
situation.
Um
but
I think it maybe if we had more details
and any kind of inclination if neighbors
are supportive, not supportive, it would
might be helpful.
>> And that's fine, Madam Chair. I I
certainly not looking for a decision
today. This this feedback is very
helpful. I I completely understand the
concern. This is not something that TID
has really done to date, acquire
property.
And uh
if you're going to do it, you have to be
committed to do it cuz it doesn't help
to get part way through it and realize I
have one or two folks that I just can't
get agree agreement with and so the
project can't move ahead. So
Um what I can tell you is the district
and their engineer are working on the
plans. They will have probably more
details as we're moving ahead in the
next 2 months. I can certainly report
back to you with maybe some more detail.
>> Do you know if they've had conversations
with any of the adjacent neighbors yet?
>> Uh I don't. I don't know that.
>> They might be very well supportive. I
don't know. I would hope cuz
you know, something to alleviate the
traffic in front of their homes.
Questions? Comments?
>> good.
>> Okay.
Well, uh
>> Does that give you enough feedback?
>> It it does. I appreciate that. Um again,
I'll I'll
I do expect over the next couple of
months we'll have some more details with
respect to the the the extent of any
right of way acquisition as the engineer
moves through the design and I can
certainly report back to you at the July
meeting with
what I know at that time.
Uh
not certainly not a decision we may need
to make uh in the next 2 months. I don't
want this to be a come to a point where
it's a
uh do or die situation. I I don't think
any of us want that.
>> Yeah. No. Appreciate the early heads-up.
>> Yeah, I got one other thought.
Uh
so the road the road upgrade you're
talking about, the three-lane section as
well as all the improvements in front of
the school.
Is is is the school's intention to to
pay for all that?
>> So, the the
tentative plan we've discussed, at least
in concept, would be that one of the
townships and I
the last discussion with Liberty
Township, they expressed some
willingness to be the applicant. Similar
arrangement to what was done on
Stockwell, what was also done on Bean
Dollar, where a township steps forward,
makes an application to OPWC,
and then as you may know, the county
offer a grant
assistance basically to match the local
shares from each local agency.
Uh that can add up to a pretty big
amount once you start
getting multiple agencies putting in
money, the county's matching share plus
the OPWC funds. And this would be, I
think, a pretty competitive project
because it's the traffic volumes, the
the scope of the work is intended for
safety and
and traffic mitigation. So, I think this
would
fare pretty well in the application
process. So,
but yet in concept, the school district
will basically make up any remaining
share of the project cost.
Yeah.
>> Thank you.
>> Great.
>> So, with that, I'll I'll move on to the
next project. No significant Plum Road,
so you're aware if if you've been past
that area recently, there is one housing
development that is under construction.
There are at least one There's at least
one other
I'd say medium-sized development that is
planned and will start within the next
year or so. They're currently running
sanitary sewer for that.
So, we're we're
we will be seeing some traffic increases
on Plum Road. This is another case where
it's a split jurisdiction. The township
line falls on the center of the road,
and so you actually have four townships
involved, much like Stockwell.
Uh so, I think the TID is in a very good
position to assist when it comes to
maybe when it comes to construction,
maybe not for right away acquisition. We
can We're not there yet, I guess is what
I'm saying, but I did want to get out
ahead of this, make sure you're aware
some of these discussions are happening
and and if you do have feedback or
thoughts, I'm certainly open to that.
>> So, you intend to upgrade all the way
from Africa Road to State Route 3?
>> Uh more than likely in phases, Pat. I
think the the first phase would likely
include the intersection at 3 B's and K
and Plumb Road. That's probably the most
uh urgent need of improvement. It's a
It's a
three-legged intersection with stop
control.
Um radio the turning radii are bad. Uh
you've got a lot of school bus traffic
going through there. It's a narrow
section of road. It's more than likely
but the first section would go from
Africa Road to
what we think would be potentially a
roundabout at that intersection.
And then potentially future phases onto
the east from that point.
>> Okay.
Thanks.
>> So, again, I'll keep you up to date as
we have more discussions on that.
Um and then the third project I wanted
to at least present again again, this is
a introduction, no decisions and and
frankly, not much planning has happened
to date, but I do anticipate working
ahead.
Uh we've had some discussions with uh
Village of Galena regarding Vance Valley
Road.
Uh
you may be aware that the Miller Farms
development uh which is kind of right at
the corner of Sunbury Road and Vance
Valley includes about 385 homes being
developed by MI Homes.
Uh
a of a lot of traffic coming out of that
area.
Uh there's already traffic on Vance
Valley Road. This will certainly add to
that. So,
um and we're in some early discussions
with the village about uh potentially
upgrading that section of road. Uh
there's a couple of uh
there's one very sharp curve right at
Joe Walker Road, and then there's
another that's uh less than desirable as
you get it toward Sunbury Road. So,
um again, this is more of a kind of
heads-up uh that we're having these
discussions. I do think um
the TID's ability to
potentially finance upfront costs um
with reimbursement from multiple sources
uh puts us in a unique, helpful
position.
Um
>> Question on that. Um
I assume M/I submitted a traffic impact
study. Do you know what uh the village
was requiring of the developer?
>> Yes, the uh
so, the development does include two
accesses. One uh road goes out Sunbury
Road. That required and has already uh
the turn lane for that entrance has
already been installed or constructed.
The second entrance is off of Vance
Valley Road, goes to the north uh from
the development.
Uh rather than having M/I Homes
construct just a a turn lane for that
particular entrance, uh we agreed to
accept a contribution in lieu of
building that turn lane, which could
both be rolled into either uh this
project or some other project that
benefits that development.
Uh M/I Homes was amenable to that. We
felt it was the the best scenario
because we knew that at some point Vance
Valley would have to be upgraded. They
have also dedicated the right-of-way
that would be needed for
uh this improvement. So, that that's one
other benefit is that's taken care of.
>> And then that intersection of Joe Walker
and Vance Valley,
whose jurisdiction is that? Is it a
mixed one or is it Galena's?
>> The intersection itself is actually
entirely within the village limits, but
you don't have to go very far east or
west before it it comes back to being a
county road in this case. So, the
county, you know, we have a vested
interest in seeing this project advance
from a county highway standpoint, but
I think this body
has the possibility of being very
helpful to help accumulate some of those
funding sources and advance something.
>> There's already a lot of traffic in that
area.
>> Yes.
So, again, nothing today. Wanted to keep
you uh
>> I think Tom had a question.
>> Yes, sorry, Tom.
>> Uh what was the process on Staunton Road
when we opened or we took that curve
out?
>> So, Staunton Road was entirely county
funded. Uh there was a developer
contribution from
Liberty Grand. They have
a They built a new intersection right at
the S curve.
Uh rather than the developer
trying to
shoehorn a turn lane in, which they
really couldn't because the the
right-of-way limitations and the
geometry that it would have been a much
larger improvement.
Uh
the county accepted a contribution in
lieu of building that turn lane, rolled
that into the project uh that that we
completed recently.
>> So,
so similar.
>> Similar.
>> Thank you.
>> Okay.
>> So, with that, that is a that is what I
know about our current projects.
Um
Moving on to next items, we already took
care of our election of officers,
and
I don't believe there's anything else I
had to share with you. Oh, um
I did you recall that the
we submitted a an application for the
ODOT TID grant program back in March. I
did run into Eddie King. Eddie is the
ODOT Jobs and Commerce representative
for Central Ohio. He did share that
the state is still reviewing those
applications and and hopes to make an
announcement sometime soon. So, no no
word yet, but we'll keep our fingers
crossed. I think that was
I'm biased, but I think that was pretty
competitive application given what's
happening in the area and the magnitude
of the project and the relatively small
ask in terms of the total project cost.
So, I'll share anything I hear
on that.
>> Great.
>> With that, that concludes my report.
Thank you.
>> All right, any other questions for Ron?
I also before we go on to our next item
wanted to acknowledge that Commissioner
Benton is here today. So, thank you for
joining us.
And next on our agenda, we have
discussion of the cybersecurity policy
requirements and we have Chris Betts
from Prosecutor's Office.
>> Good morning, board members.
>> Good morning.
>> Christopher Betts with the
Prosecutor's Office on behalf of Melissa
Schiffel, Delaware County Prosecutor. I
appreciate you having me here this
morning. I can't believe we're talking
about summer interns already. I mean,
I'm glad it's summer, but
this year's flown by so far.
>> It has.
>> Um in any event,
um
the legislature enacted
under House Bill 96 back in the last
half of last year um
Revised Code 9.64,
which requires all political
subdivisions to have a cybersecurity
policy.
Um it's kind of strange that we're
talking about this with this board
because this board doesn't own or
maintain, to my knowledge, at least in
discussions with Rob,
um, any computer networks,
um, computers, etc. Um, probably some
data, uh, that that's maintained as far
as this board is concerned, but
everything else is is sort of maintained
under the umbrella of the county,
um, through the engineer's office or
other offices. So, it's kind of
interesting that we're talking about
this, but this still applies to the TID
in the sense that the TID is a political
subdivision,
um, at least as that's defined under the
statute. It's a body corporate and
politic that's smaller than the state,
and all of those are required to have
cybersecurity policies under the new
statute.
So, um, I just started discussing this
with Rob yesterday as to to where we go
with this.
Uh, the requirements were, um,
the statute became effective on
September 30th of last year,
um, and we need to have it talks in
terms of a uh, a cybersecurity program,
which really equates to a policy. Um,
what I have understood is that the
auditor is going to start looking for
this, at least as far as the counties
were concerned and the cities were
concerned, at the beginning of 2026.
Um, the other political subdivisions,
which would include this board, um,
they're going to start looking for that,
uh, starting July 1st of 2026. So, it's
something we need to kind of hop on and
get done.
Um, certainly don't want to create
anything that's cumbersome or burdensome
to this board, uh, but also want to
comply with the statute. So, one of the
things that that Rob and I had talked
about and are potentially looking into
and we'll discuss more, uh, before the
July meeting, uh, is whether we can go
ahead and and adopt, uh, or this board
can adopt what the county has adopted.
Um, my understanding is that Steve
Lewis, who is in charge of, um, IT for
the county has created uh,
a policy for this
and that's something that we could look
at potentially going ahead and adopting
rather than reinventing the wheel
and something that if the board at some
point does own its own computers,
computer infrastructure, etc.
That that can be implemented and used.
But we'll need to see what's in there. I
know one of the things that Rob was
concerned about was uh, you know, making
sure that any vendors or contractors
that the board would contract with have
sufficient
policies or programs in place for
cybersecurity.
I'm not sure exactly. I have not seen
specifically what's in um,
Steve Lewis's policy, the the one that
he drafted for the county, but we could
take a look at that and see if that is
covered in there as well.
It's not something that is specifically
as far as vendors and contractors is
um, addressed in the statute expressly.
There are about six items in there that
are in the statute that need to be in or
should be in your cybersecurity policy.
Um, those include, you know, identifying
this, you know, various threats and how
you're going to respond and
there's a training component in there as
well that applies to any employees. My
understanding is this board doesn't have
really have any employees so just board
members so we'll have to look at that as
well.
But in any event, hopefully most of
those things are addressed in in what
Steve has
already created so that we don't have to
reinvent that wheel.
If there's things that we need to add to
it, certainly we can that are specific
to this board, we can certainly look at
those and and go ahead and
you know, do any sort of amendment or
addition that we need to do
to to bring that policy
as being functional for the board. But
it's certainly something that that as
audits go forward in the future Um, we
want to make sure that we have. I don't
think that there's going to be, or at
least my understanding is that there's
not going to be cybersecurity policy
police out there checking to make sure
if you have a policy come July 1st, but
we want to be as close as we possibly
can uh, you know, to that date.
Um, I think it's going to be a lot like
public records policies where the
auditors, you know, ask to see it. Okay,
check mark star, you've got one kind of
a thing. Frankly, they're kind of
numbers people, so I don't know that
they're going to look into the technical
part of it, but we want to make sure
that technical part is is good to go,
and I, you know, I think Steve's been
with the county for a long time, so I
think he's probably drafted something
that that
um, is a good workable policy that we
can just sort of build on and and, you
know, covers those bases as a matter of
of protection and good public policy.
So, I'm happy to answer any questions.
Again, it was something that that Rob
and I just started discussing yesterday,
um, and we'll pull Steve's policy and
see what it says. We'll be back with the
board in July, um, and see where we go
from there in terms of of adopting
something.
>> All right, Chris. Yeah, three of us on
this board are already on another board
where that's being discussed.
>> Mhm.
>> And,
you know,
the way the way I look at it is that
it's a risk management transfer.
All right. So,
I I I'd like to have you, if you could,
give us a copies of Steve Lewis's policy
in advance,
>> Certainly.
>> so we can all look at it. But, my whole
point is, since we we don't have any IT
infrastructure, and don't plan to,
then then the idea of all this is to be
sure the risk is properly transferred to
the proper entity,
make the entity responsible for
complying with the code, and assuring us
annually that we are that they are
complying with the code, which to me
meets our obligation under the statute.
>> Mhm.
>> So, that's really what I'm looking at
here is total risk transfer away from
the board.
So,
I'd be interested to see what Steve has
on that.
>> Yeah, no, I totally understand where
you're coming from and and frankly,
um part of my discussion with Rob
yesterday was that, you know, the county
has to have this in the first place and
we certainly don't want to create
something duplicate to what the county
is doing, but the county should be
complying with all of those things in
the first place and I understand the
board wanting some assurance that you
know, that the offices that are that are
involved with this board, such as the
engineers office, you know, are in
compliance and can give some sort of an
assurance on an annual basis. So, I I
understand where you're coming from with
it.
>> Well, here's another question then.
All the counties in NCAs,
it appears, at least the one that we're
on,
is creating its own policy.
>> Mhm.
>> Is this proper going forward or should
all the NCAs be under the same policy
the county has?
>> I can't answer that.
>> Yeah, I'm not I'm not exactly sure um as
far as the NCAs are concerned and and
you know, I'm not the legal advisor to
the NCAs, so.
>> That's That's what I don't understand is
uh
they they're pretty much separate
entities from the from the county
offices, is that it? So, they can create
their own policies?
>> If you qualify as a political
subdivision under the statute, which
means that you're a body corporate and
politic that's smaller than the state,
you have to have one. What that looks
like
um could be different for different
entities. Again, there's six different
things that are in the statute that
are supposed to be in your be in your
policy or covered by your policy
um and you know, there there would be
different ways to
to write that, draft that or incorporate
it that would be specific to those
entities.
Um and you know, certainly we want to
look at whatever, you know, Steve's put
together and and see if it's something
that's workable for
um
this board. I presume that it probably
is.
Um but we'll take a look at that and
I'll certainly forward um
I can forward it to Rob. Rob can you
forward it on to the board members?
To have a copy in advance then?
>> Okay, thank you, Chris.
>> Sure, absolutely.
>> Thank you. Do we need to pass it before
July 1st? Should we be having a meeting
in June?
>> I think
you're supposed to have it by July 1st.
Again, I don't think that there's going
to be cybersecurity police that are out
there on July 1st that are looking to
make sure that you have the policy. I
think they're going to check it as a
part of your next audit to make sure
that you have it in place.
Um so, I think having it in place
um as soon as possible
either before or shortly after July 1st
>> Okay.
>> uh will um satisfy the auditors.
Um so, I think um I'm not sure when the
July meeting is scheduled. Um I'm
assuming it's probably the first half of
July.
>> Yes, July 8th is sufficient.
>> Yes.
>> July 8th. So, I think that's probably
sufficient for making sure that we have
something in place as soon as possible
or as close to that date as possible.
>> Thank you very much.
>> Sure. Any other questions?
>> Thanks for the explanation.
>> No problem. Thanks for having me.
>> Thank you, Chris.
>> Okay, down to resolution
2026-03
approving plans, specifications, and
estimates for improvements to Stockwell
Road and authorizing the county engineer
to advertise for bids. Rob.
>> Uh yes, thank you. Uh as I sort of teed
up in my report, uh we have completed
the plans and specs for this project.
Uh our schedule would be to
uh for bids uh within about the next
week
and then uh receive bids in June and
have a contract uh ready for you at the
July 8th meeting.
Uh current estimate for the project is
about $950,000
uh which is within the the budget we had
uh identified up front in the project
agreement. And so this project would act
and look very much like the uh Bynum
project that we undertook uh
a while ago.
Uh the county engineer would essentially
handle all the
management, construction engineering, uh
um
basically the the TID board would be
paying the invoices or SI would be
paying the invoices, I'd just say, and
then issue um
reimbursement invoices at the completion
of the job. So, um
glad to answer any questions.
>> Any questions?
>> No, no questions. I'm going to make a
motion we
approve this resolution.
>> Second.
>> Any further discussion?
If not, all in favor?
>> Aye.
>> Aye.
>> Aye.
>> Motion carries.
Good to see the project moving forward.
Thanks, Rob, for everybody's efforts on
that.
Any other business?
All right. I know we just talked about
it, but it looks like the next meeting
and so it sounds like we won't need
June.
>> Um
the only thing that we would have would
be the discussion of a cybersecurity
policy and and Chris uh Betts and I have
some work to do on that, so I I'm just
not sure that that warrants a a June
meeting at this time. Um so I
I've been planning uh that we would not
have a June meeting until July. I think
works for our purposes, my purposes at
least.
>> July 8th.
>> I don't like
Hopefully that works for everyone. I
likely won't be here, but I don't need
to be here, So.
As long as we have a quorum.
All right, if there's nothing else