DELAWARE, Ohio — The Delaware County Board of Commissioners on May 4 held a viewing of a petition to include the Bainbridge Mills Phase One subdivision in the county’s drainage maintenance program, a procedural step that drew questions from residents about potential costs and construction impacts.

The viewing, conducted using drone video technology, allowed commissioners to observe the subdivision’s stormwater infrastructure. No testimony was taken and no decisions were made. The first public hearing is scheduled for Aug. 3, 2026, at 10 a.m.

Brett Bacon, deputy administrator for the Soil and Water Conservation District, told commissioners that Phase Two of Bainbridge Mills is already under county maintenance because it was platted after July 1, 1998, when a requirement for inclusion took effect. Phase One was built before that date and is not covered.

“Phase one missed the enactment of that requirement through the platting regulations,” Bacon said.

The petition seeks to add Phase One’s stormwater system — including two dry detention basins and underground pipes — to the county’s maintenance program. Bacon said the infrastructure is typical for a pre-1998 subdivision and that he has not seen any indications of major problems.

“Nothing jumps out at me in this subdivision that throws up red flags right now,” he said.

Residents attending the viewing asked about potential costs and the scope of any construction work. Bacon said that if the petition is approved, each parcel would be assessed 0.3 mills for ongoing maintenance. Any construction costs would be split equally among property owners.

Jamie Byerly, a resident of Sable Court, asked for details about what construction might entail. Bacon said no inspection has been conducted and that the extent of any needed work is unknown.

“We don’t know at this point because we haven’t done the inspection,” he said. “Your hope is you go out here and find that the system is good and doesn’t require repair.”

Commissioner Marrow noted that the process is unfamiliar to many residents but routine for the county, which oversees maintenance for about 670 subdivisions.

“This is unique for you. This is fairly typical for us,” he said.

The Aug. 3 hearing will include a report from the engineer’s office and allow landowners to testify for or against the petition. Commissioners could then decide whether to proceed to a second hearing.